For Work Not Performed, a Contractor Wins a Settlement

10/11/16

By Mark Reutter, BaltimoreBrew

The Brew has written extensively about overruns in road, water and other contracts that result in millions of dollars paid out by Baltimore taxpayers. They are called Extra Work Orders (EWOs), and examples are here, here and here.

This article is about a cost underrun that resulted in the payment of $518,120.18 to a private contractor by the Board of Estimates on Wednesday.

All of the board members approved the award, including Mayor Stephanie Rawlings-Blake, Acting City Solicitor David Ralph, Public Works Director Rudy Chow, Comptroller Joan Pratt, and Council President Bernard C. “Jack” Young, who was represented by Councilman Ed Reisinger.