Replacement of Failing Colgate Creek Bridge is 26% Over Budget – and Construction Hasn’t Even Begun

3/10/21

By Mark Reutter, BaltimoreBrew

Project TR 16301, replacing the Broening Highway bridge over Colgate Creek, is special even by Baltimore contracting standards: it hasn’t yet started, but it’s already 26.1% over budget.

A $4,641,050.84 EWO (extra work order) was approved by the Board of Estimates – unanimously and without discussion – last month, even though construction won’t get underway until spring or early summer.

That’s spring or early summer 2021, despite the “Progress Ahead” signs the city Department of Transportation has erected along Broening Highway announcing the replacement bridge was completed last December.

READ FULL ARTICLE HERE

Recent Deals

Interested in advertising your deals? Contact Edwin Warfield.

Connect with these Baltimore Professionals on LinkedIn

  • Edwin Warfield

    Editor in Chief, Warfield Digital

    Connect
  • Jean Halle

    Independent Consultant

    Connect
  • Larry Lichtenauer

    President of Lawrence Howard & Associates

    Connect
  • Newt Fowler

    Partner at Womble Carlyle, LLP

    Connect
  • David Crowley

    Owner at Develop DC

    Connect
  • Carolyn Stinson

    Stinson Marketing Group

    Connect